Flagstaff – Grandview Drive Reconstruction Project to Begin Tuesday

On Tuesday, Sept. 5 the City of Flagstaff and its contractor, Eagle Mountain Construction, will begin the utility installation phase of the Grandview Drive Reconstruction Project as part of the Spruce Wash Flood Mitigation suite of projects. Starting on Tuesday, crews will begin setting up traffic control and mobilizing equipment into the work zone along Main Street, just south of Cedar Avenue. Crews will also begin removing the existing asphalt pavement in preparation for sewer infrastructure installation.

Construction will begin on Main Street, just south of Cedar Avenue. Lane shifts on Cedar Avenue will occur during the construction of the sewer main on Main Street south of Cedar but both east and west bound traffic on Cedar will be maintained at all times.

Once construction activities move north of Cedar Avenue, Grandview Drive will be closed to thru traffic, with access to residents only. The contractor will work to ensure access to properties throughout the duration of the project, however, access may be closed for short durations when installing new utilities or concrete. The contractor will work with property owners and tenants on an individual basis to coordinate this work. Residential access for mail, deliveries, trash, recycling and emergency services will be maintained throughout construction. Additionally, the contractor will make every attempt to ensure continuous water service to all properties over the duration of the project; however, brief water shut offs will be required to tie into the City’s existing system. Those affected will be notified in advance of any temporary utility interruption. The contractor may temporarily remove sandbags and flood mitigation measures when needed to install utilities. Crews will return or replace them to their original location following installation operations. Please note that residents are not advised to remove any flood mitigation measures during construction.

The utility phase of this project includes the installation of new sewer and water mains and services along a section of Main Street, just south of Cedar Avenue, and along Grandview Drive from Cedar Avenue to Linda Vista Drive (including the adjacent cul-de-sacs). This utility work is being done to lower and replace the aging underground utility facilities prior to the reconstruction of the roadway with a lowered and inverted crown. Following the utility phase, full street reconstruction will take place; which includes new curbs, gutters and an inverted asphalt pavement roadway along Grandview Drive to increase the amount of water that the road can accommodate during a flood event. The utility phase of this project is set to be complete in spring 2024.

LEAVE A REPLY

Please enter your comment!
Please enter your name here